Electrical Requirements
WARNING
The following information is provided for hooking up electrical
supply to the spa. This work must be performed by a qualified licensed
electrician. Failure to have this done can result in termination
of all warranty coverage and also create an extremely dangerous
bathing environment.
240-VOLT INSTALLATION PROCEDURE
1. The correctly sized GFCI circuit breaker
must be installed at the main electrical service panel. In addition,
a properly suited shut-off switch must also be installed in plain
view of the spa. This is in compliance with section 422-20 of the
National Electrical Code, ANSI/NFPA 70-1987. The electrical service
panel must be readily accessible to the spa occupant but must not
be within 5 feet of the spa.
2. After spa has been positioned, route line through knockout on
the left or right front of spa cabinet.
3. Route line inside cabinet to the hole provided under or behind
control box through hole provided.
5. Attach wires to the terminal block inside control box. Refer
to the 240V wiring diagram inside the front face plate of
the control box and adjacent to terminal block for final connection
instructions.
6. Complete wire connections at main service panel GFCI breaker.
7. Do not turn power on until instructed to do so in the "SPA
START UP" section.
NOTE: Several bonding lugs are provided on
the control box and other components
located inside the equipment compartment of the spa. Connect a No.8
AWG (8.4mm) solid copper conductor to these lugs and any metal object
within 5 feet (1.5m) of the spa.